Section 3 of 10

Architectural Coordination Drawings

Floor plans, ceiling plans, device layouts, and mounting details for GC and architect coordination.

Total Documents

10

in this section

Auto-Generated

6

from model

Manual / Template

4

require input

Complete

2

documents

Outstanding

8

remaining

Section Completion20%
2 complete4 in progress4 not started
10 documents
IDDocument NameTypeMethodStatusLast ModifiedActions
3-01AV Floor PlansDrawingAutoDraftAug 2, 2026
3-02Device Location PlansDrawingAutoDraftAug 2, 2026
3-03Reflected Ceiling PlansDrawingAutoDraftJul 30, 2026
3-04Display & Projection LayoutsDrawingAutoCompleteAug 1, 2026
3-05Speaker & Microphone LayoutsDrawingAutoDraftJul 28, 2026
3-06Camera Placement & CoverageDrawingAutoNot Started
3-07Equipment Room & Rack LocationsDrawingManualCompleteJul 25, 2026
3-08Furniture & Table CoordinationDrawingManualNot Started
3-09Wall ElevationsDrawingManualNot Started
3-10Mounting & Installation DetailsDrawingTemplateNot Started